1月31日18时18分,随着武金堤公路站-复兴路站区间左线盾构机接收,隧道第552环管片也是该线最后一环管片拼装完成,标志着武汉轨道交通5号线实现全线双线贯通。
武汉轨道交通5号线工程全线共23个地下区间(含出入场线),地质条件复杂,其中10个区间穿越长江一级阶地,13个区间穿越长江二、三级阶地,局部区间穿越岩溶发育区及软土地层。沿线区间周边环境状况复杂,彭刘杨路站-司门口站区间采用矿山法穿越蛇山硬岩地层,多个区间下穿铁路路基、桥梁;既有建(构)筑物;市政桥梁、综合管廊;既有地铁区间等重大难点。
轨道交通5号线工程线路全长35.2公里,南起南三环,北至武汉火车站。全线共设站25座,主体结构已全部完工,正在进行站内公共区装修。全线轨道74.2公里,累计已完成69.2公里。
Yangshan Tunnel in Qixingguan District, Shenzhen Officially Opens to Traffic
下一篇Transportation Projects in Guangming District, Shenzhen Progress in an Orderly Manner

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)