1月29日,中礼区间明挖段主体结构下穿石油管道处结构顶顺利完成回填,标志着下穿石油管道暗挖施工二级风险消除,同时也标志着历时3年建设的南昌地铁4号线1标段实现全线贯通。
为实现这一目标,南昌地铁面对首次近距离下穿输油管道施工(管棚距离输油管道1.5m),共累积召开了9次专家评审会,根据专家意见不断完善设计及施工方案,做到万无一失。经过3个月24小时不间断施工,并严格进行风险管控,实时监测地表沉降、洞内周边收敛、油气监测、周边建筑物及管线监测,控制在设计容许沉降值范围内,最终圆满完成节点建设任务。
Both Tunnels of the Shield-Driven Section from Qifeng Road Station to Qili Station on Nanchang Metro Line 4, Which Passes Under the Beijing-Kowloon Railway Bridge, Have Been Successfully Completed
下一篇Yangshan Tunnel in Qixingguan District, Shenzhen Officially Opens to Traffic

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)