At the viaduct construction site in Xiantao urban area, nearly 100 UHPC-NC composite bent caps have been completed. This new material, known as "super concrete," has compressive strength 5 to 8 times that of traditional concrete and is being applied on a large scale in the main works of an expressway for the first time in China.

"UHPC is extremely sensitive to temperature and humidity, and construction in hot weather requires even more precise control," the technical director said, pointing to the UHPC bent cap formwork being poured. "We further optimized the rebar layout, introduced positioning fixtures, and used BIM model simulation to cut the on-site installation time for a single formwork to under half an hour, completely moving away from the traditional cast-in-place bracket process."
As of now, for the left carriageway of the Xiantao urban viaduct, 96% of pile foundations, 62% of piers and columns, 45% of UHPC-NC composite bent caps, and 44% of conventional bent caps have been completed. Once the viaduct is built, the space beneath it will be freed up for an 8-lane municipal road, thoroughly resolving the urban area's dilemma of "limited clearance and cramped sites."
Source:Jingchu Net
Key Milestone in Dali Airport Phase III Expansion and Renovation: Trial Piles Begin Drilling for Terminal 3
下一篇Beijing Vibroflotation's Plum-Blossom Guide Rod Solves Deep-Hole Liquefiable Foundation Challenge

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)