        Recently, the pile foundation construction of the Baishawan International Healing Resort Hotel project, undertaken by the Second Company of CCCC First Harbor Engineering Co., Ltd., was successfully completed.

  The project is located in Fangchenggang City, Guangxi Zhuang Autonomous Region. Its construction scope includes hotel guest rooms, a lobby, dining rooms, and other facilities, with a total floor area of approximately 29,700 square meters and a maximum building height of 23.95 meters. The project has a total of 848 PHC high-strength prestressed concrete pipe piles. During construction, the team strictly adhered to codes and standards, precisely controlled parameters such as pile position, pile length, pile verticality, and hammering operations, and efficiently completed the pile foundation construction milestone.