In Hebei Province, the L7 bid section of the Quyang-Gangzhou Expressway has achieved a 100% return-to-work rate among management and labor personnel, with 42 sets of large construction equipment, including rollers and excavators, in place simultaneously.

The project has overcome the impact of snowfall and low temperatures through measures such as insulating the subgrade with covers and heating and curing concrete, steadily advancing construction including subgrade filling and soft foundation treatment, and making every effort to push forward subgrade filling, soft foundation treatment, bridge pile foundation and other construction work.
As of now, the project has completed 25.1% of subgrade filling, 64.61% of soft foundation treatment, and 67.31% of pile foundations.
Source: The Paper
Pile Foundation Construction of National Highway 230 Project Reaches 58% Completion
下一篇Pile Foundation Construction in Full Swing for Hangzhou Metro Line 18 TOD Project

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)