12月22日,由湖北省路桥集团有限公司承建的二广高速荆州绕城段弥市镇片区工程建设有序推进,控制性工程松虎河特大桥施工实现阶段性突破,为项目整体推进奠定坚实基础。

截至目前,各分项工程进展顺利。具体来看,桩基工程完成1485根,完成率77.8%;系梁工程完成244道,完成率24.2%;承台工程完成11处,完成率34.28%;墩柱工程完成453根,完成率25.03%;预制箱梁完成130片,完成率3.27%。
该标段位于荆州市荆州区弥市镇境内,路线全长12.151公里。