Recently, the lower reservoir dam of the Xinjiang Hami Pumped Storage Power Station, for which the Northwest Institute undertook the survey and design tasks, was successfully topped out. The complete fulfillment of this key milestone marks another major milestone achievement in the station's construction, laying a solid foundation for subsequent water impoundment and power generation as well as the project's on-schedule commissioning.
The Xinjiang Hami Pumped Storage Power Station is located in Tianshan Township, about 54 kilometers northeast of Hami City. The station has a rated head of 474 meters and an installed capacity of 1,200 megawatts. It consists of structures including the upper reservoir, lower reservoir, water conveyance system, underground powerhouse system, and switch station. The upper reservoir dam was successfully topped out on August 30, 2025. The lower reservoir dam topped out this time is a reinforced concrete face rockfill dam with a maximum dam height of 81 meters and a crest length of 504 meters.
Since the start of dam filling construction, in the face of numerous challenges such as complex geological conditions, a short effective construction period, a mismatch between supply and demand of dam-fill materials, and high-intensity filling operations, the design team of the Northwest Institute worked closely with all participating units, adjusting and improving the plan in line with on-site conditions as the project progressed, and strictly controlling the process, thereby ensuring that the project achieved the goal of topping out the lower reservoir dam on schedule.
CGN Shilou Longjiao Phase IV 100 MW Wind Power Project Commences Construction
下一篇Gate Closure and Impoundment! China's Highest-Altitude Double-Curvature Arch Dam Power Station Under Construction Reaches Major Milestone

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)