Hubei Engineering Company Wins Bids for 4 Projects

2025-09-19 4835 0人评论

Recently, Hubei Engineering Company successfully won the bids for the EPC and operation & maintenance project of the 35 kV construction power supply system for the Jiangxi Xunwu Pumped Storage Power Station, the general contracting project of the Hubei Changyang Longzhouping Town All-Vanadium Flow Battery Energy Storage Station, the construction and installation works project of the Inner Mongolia Energy Huade 500 MW/2,000 MWh Independent Energy Storage Project, and the design and technical services for the reconstruction project of the Iraq Al-Dora 4x160 MW Thermal Power Plant.

The Jiangxi Xunwu Pumped Storage Power Station is located in Ganzhou City, Jiangxi Province. It is a key project of the national "14th Five-Year Plan" with a total installed capacity of 1,200 MW and is a Class I large (Type 1) water conservancy project. Upon completion, its annual power generation can meet the annual electricity demand of approximately 750,000 households, enhance the peak-shaving capacity of the Jiangxi power grid by 3 million kW, save 470,000 tons of standard coal per year, reduce carbon dioxide emissions by 1.17 million tons, and achieve a full-life-cycle emission reduction of more than 65 million tons, which is of great significance to Jiangxi's energy supply security and energy conservation and emission reduction.

The general contracting project of the Hubei Changyang Longzhouping Town All-Vanadium Flow Battery Energy Storage Station is located in the Economic Development Zone of Changyang County, Hubei Province, with a total capacity of 50 MW/200 MWh. Upon completion, the project will greatly enhance the stability and reliability of electricity in the Yichang area, effectively respond to the growing local electricity demand, and promote local economic development.

The construction and installation works project of the Inner Mongolia Energy Huade 500 MW/2,000 MWh Independent Energy Storage Project is located in Huade County, Ulanqab City, Inner Mongolia Autonomous Region, and is one of the first batch of independent energy storage demonstration projects in Inner Mongolia Autonomous Region in 2025. Upon completion, the project will help absorb hundreds of millions of kWh of clean electricity annually, strongly promote regional green and low-carbon development, and have exemplary benchmark significance for verifying the outward transmission capacity of "energy storage + new energy base," exploring the mechanism for independent energy storage to participate in electricity spot market trading, and promoting the industrialization and application of advanced energy storage technologies.

The reconstruction project of the Iraq Al-Dora 4x160 MW Thermal Power Plant is located in the Al-Rashid administrative district of Al-Dora, Baghdad, Iraq. It is equipped with 4 sets of oil-fired generating units, each with a rated output of 160 MW, and the project is planned to be reconstructed through new construction, repair, and reuse of existing facilities. Upon completion, the project will significantly enhance Iraq's power supply capacity, provide sustainable energy for the stable operation of the power grid in the relevant areas, and strongly boost local economic development.