Recently, the KR150M multifunctional rotary drilling rig on a Caterpillar chassis, developed by Jiangsu TYSIM Piling Equipment Co., Ltd. (hereinafter referred to as "TYSIM"), has performed outstandingly in construction projects in Turkey, injecting strong momentum into local infrastructure development and further consolidating TYSIM's important position in the Turkish market.
Recently, the KR150M multifunctional rotary drilling rig with Caterpillar chassis, developed by TYSIM Piling Equipment Co., Ltd. (hereinafter referred to as "TYSIM"), has performed outstandingly in construction projects in Turkey. It has injected strong impetus into local infrastructure development and further consolidated TYSIM's important position in the Turkey market.

Precise operation to overcome soil construction difficulties Precise operation to overcome soil construction difficulties In this Turkish infrastructure project, the construction requirements of an 800mm drilling diameter and 20m hole depth, combined with the geological challenges of complex soil layers, posed a severe test for piling equipment. However, TYSIM's KR150M, with its tailor-made customized design, turned these challenges into a stage to demonstrate its strength. Its high-efficiency drilling system, like a precise "geological scalpel", maintains a stable pace in variable soil layers, improving construction efficiency by nearly 30% compared with traditional equipment, while keeping the transport width within 3 meters, perfectly meeting the width restrictions for transportation on Turkey's mountain roads. In this Turkey construction project, the rigid specifications of an 800mm drilling diameter and 20m hole depth, coupled with the geological challenges of complex soil layers, posed a severe test for engineering equipment. However, TYSIM's KR150M, with its tailor-made design ingenuity, turned these challenges into a stage to demonstrate its strength. Its high-efficiency drilling system, like a precise "geological scalpel", maintains a stable pace even in variable soil layers, improving construction efficiency by nearly 30% compared with traditional equipment. It also strictly controls the transportation width within 3 meters with perfect precision, perfectly meeting the width restrictions for transportation on Turkey's mountain roads. Excellent performance, adapted to the Turkish construction environment Excellent performance, adapted to the Turkish construction environment Turkey's construction environment is a litmus test for the "comprehensive capabilities" of piling equipment — sustained high temperatures in summer, potential disruptions from geological faults, and stringent constraints of environmental regulations, none of which can be overlooked. The KR150M's original Caterpillar engine acts like a powerful "power core", continuously delivering stable power with high reliability at around 40°C; TYSIM's independently developed electronic control and hydraulic systems, like a precision "nerve center", make every operation precisely controllable. Turkey's construction environment serves as a litmus test for the "comprehensive capabilities" of equipment — including sustained high temperatures in summer, potential disruptions from geological faults, and stringent constraints of environmental regulations, none of which can be overlooked. The KR150M is equipped with an original Caterpillar engine, which acts like a powerful "power core" and, with high reliability, continuously delivers stable power even at 40°C. TYSIM's independently developed electronic control and hydraulic systems, resembling a precision "nerve center", ensure every operation is precisely controllable. Deepen cooperation and strengthen exchanges between China and Turkey Deepen cooperation and strengthen exchanges between China and Turkey The bond between TYSIM and Turkey has long gone beyond simple equipment supply. From the careful commissioning of the first batch of equipment to dozens of units now entering the market, behind this lies deep trust accumulated through repeated technical communications and service responses. The outstanding performance of the KR150M has further strengthened this trust — Turkish customers have organized delegations to visit TYSIM's headquarters in Wuxi multiple times, conducting immersive inspections of the entire process from design to mass production, from R&D workshops to testing grounds. Such in-depth interaction not only allows local partners to better understand the details of Chinese intelligent manufacturing, but also enables the TYSIM team to accurately capture the individualized needs of the Turkish market, driving product iteration toward localized customization. In the future, TYSIM will continue to take technological innovation as its core and localized service as its focus. On the infrastructure blueprint of Anatolia, it will write more stories of Chinese intelligent manufacturing resonating with Turkish needs, promoting the common development of China and Turkey. The bond between TYSIM and Turkey has long gone far beyond simple equipment supply. From the careful debugging of the first batch of equipment to dozens of units entering the market today, behind this lies deep trust accumulated through countless technical communications and service responses. The outstanding performance of the KR150M has only made this trust grow stronger – Turkey customers have organized delegations to visit TYSIM's headquarters in Wuxi many times, conducting in-depth inspections of the entire product process from design to mass production, from R&D workshops to testing grounds. Such in-depth interactions have not only allowed local partners to better understand the details of Chinese intelligent manufacturing but also enabled TYSIM's team to accurately capture the individualized needs of the Turkey market, driving product iterations towards localized customization. In the future, TYSIM will continue to focus on technological innovation as its core and localized services as its priority. On the infrastructure blueprint of Anatolia, it will write more stories of resonance between Chinese intelligent manufacturing and Turkey needs, promoting the common development of China and Turkey.





Foundation Academy | Foundation Expert - Lao Zhu Lecture Hall (Episode 52): Tang Xiangjun -- Research and Application of the Reverse Circulation Cast-in-Place DTH Hammer Pile Formation Method
下一篇Company News | Ultra-difficult Strata, Ultra-deep Construction! Shangong Machinery's TRD-80EA Trench Cutter Sets a New Record for TRD Method Construction in the Nanjing Region, Continuing to "Create Miracles"!

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project