On July 7 local time, the main works under Supplementary Agreement No. 3 of the 25-kilometer road rehabilitation project on Nosy Be Island, Madagascar, undertaken by Sinohydro Bureau 14, were completed ahead of schedule.
The supplementary agreement was formally signed on February 18, 2025, with an original construction period running until July 15. It mainly covers the rehabilitation of approximately 8 kilometers of road, including earthworks, drainage works, main construction centered on pavement works, and ancillary supporting works such as the installation of traffic signals and signs.
Faced with complex traffic diversion pressures and restricted construction site conditions, the project team scientifically prepared the construction organization plan during the preliminary stage and innovatively adopted a advancement model combining optimized process interleaving, segmented flow-line operations, and skip-segment parallel construction. After three months of intensive work during the rainy season and a two-month high-intensity "60-day sprint" in the dry season, the main works under the agreement were ultimately completed one week ahead of schedule, achieving the "dual targets" of project quality and construction progress.
Since entering Nosy Be Island, Madagascar, in 2020, Sinohydro Bureau 14 has consistently focused on high-quality contract performance and continued to demonstrate its comprehensive corporate strength. It has not only established a good corporate image locally but also won the high trust of the local government and the owner, fully demonstrating PowerChina's sense of responsibility and mission in overseas markets.
Major Strategic Project of the "Belt and Road" International Production Capacity Cooperation Successfully Completes Mechanical Completion
下一篇Company News | Guangdong Provincial Academy of Building Research's subsidiary Zongzhan Co., Ltd. wins First Prize for Science and Technology Award from the Provincial Engineering Survey and Design Industry Association

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)