In the height of summer in August
Sichuan is bustling with construction activity everywhere
Tunneling, mucking, rock bolting, shotcreting...
As XCMG's XTR4/260 cantilever tunnel boring machine
breaks through the tunnel face
the 715-meter-long Miaozidong Tunnel has been successfully holed through
opening up a key link for the entire project's construction

The XCMG XTR4/260 entered the tunnel in late March
The excavation advance rate is 8-15 m per day
with a monthly advance of no less than 200 m
The construction progress is one and a half months ahead of the original schedule
greatly accelerating the project's construction progress
The tunnel is mainly composed of Class IV and V surrounding rock, and is a small-section water conservancy tunnel 3 m wide and 2.8 m high. The traditional drill-and-blast method has low efficiency and high cost. After study by the project department, it was finally decided to use the XCMG ** XTR4/260 cantilever tunnel boring machine, whose body is only 2.1 m wide, for construction.

The XCMG XTR4/260 tunnel boring machine has the narrowest body in China and is equipped with a large-taper cutting head, featuring high cutting force, strong rock-breaking capability, and low cutting vibration. It performs particularly well in controlling overbreak and underbreak, saving a large amount of shotcrete. The packing seat adopts a spiral sealing structure, effectively preventing dust ingress and enhancing product reliability. The use of mechanical excavation effectively reduces the labor intensity of frontline workers.

It is reported that this project is one of the "172" major water conservancy projects designated by the State Council, and is also an important component of Sichuan Province's "five horizontal and six vertical" water diversion and replenishment ecological water network. XCMG's tunnel boring machine has delivered efficient construction and won unanimous praise from customers, earning acclaim for the XCMG brand.
XCMG will focus on the market and customer needs
and continuously develop new products with high added value and high technology content
to further expand the tunnel market
and provide technical support
Warmly Celebrate the Successful Launch of the "Blue Ocean Haiguang No. 01"!
下一篇Quanzhou Goes All Out to Advance Project Construction

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)