With the precise erection of the last 13-meter hollow slab beam, the first "pile" + "component" project in the Yangjiang region undertaken by Jianhua Building Materials Yangjiang Company has come to a successful conclusion. The project is uniquely innovative in its design: the substructure innovatively adopts PRC-700AB130+UHC-700AB-130 to replace the original cast-in-place pile scheme, successfully saving the client about 20% of the project cost and shortening the construction period by 26 days. The superstructure cleverly uses a 13-meter post-tensioned precast hollow slab beam design, greatly shortening the project duration and laying a solid foundation for the efficient advancement of the project.


01. Multiple parties join hands to facilitate efficient project progress
Throughout the project advancement, Jianhua Building Materials Yangjiang Company and China Railway Construction Engineering worked closely together in full cooperation. The supervision unit and the owner unit also actively participated in the production of the first hollow slab beam. After production was completed, the owner and the general contractor, together with a third-party testing unit, carried out strict testing on the hollow slab beam, and the results were successfully passed. The outstanding performance of Jianhua Building Materials Yangjiang Company won unanimous high recognition from the owner and the general contractor.

02. The project is of great significance and far-reaching influence
With the imminent completion and opening of the Guangzhou-Zhanjiang High-Speed Railway, Zhanjiang North Station will transform into a key transportation hub connecting the Pearl River Delta and the western Guangdong region. This project is not only of extraordinary significance to the construction of Zhanjiang North Station on the Guangzhou-Zhanjiang High-Speed Railway, but is also an important part of urban development in Xiashan District, Zhanjiang City, and will powerfully promote local economic prosperity and social progress.

03. Joint efforts to create a new future for transportation

It is believed that with the joint efforts of all parties, this transportation hub will bring the public a more convenient and efficient travel experience and write a new glorious chapter for regional development.
'Foundation Expert - Lao Zhu's Lecture Hall' Episode 4 Delivers Exciting Content, Setting New Popularity Highs!
下一篇A Shining Star in Adversity: Zoomlion Service Engineer Liu Yaowen's Extraordinary Journey in Nigeria

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project