Recently, the dual-mode shield machine mode conversion commissioning and acceptance for the right line of the Huangmabu Station to Shiyan Center Station section (referred to as the "Huang-Shi section") of the Shenzhen-Daya Bay Intercity Railway was successfully completed, marking the successful completion of the shield machine's transition from split to integral configuration and its first excavation mode conversion.
The Huang-Shi section has a total length of 7.837 kilometers and features long-distance hard rock, upper-soft lower-hard strata, and soft soil strata, with extremely complex geological conditions that a single excavation mode of the shield machine cannot satisfy the construction requirements. Based on actual site conditions, the project team deployed four "EPB + TBM" dual-mode shield machines, launching from the working shaft of the Huang-Shi section and being lifted out at Huangmabu Station and Shiyan Center Station respectively. When entering long-distance ultra-hard rock strata, the shield machines can switch to TBM mode for excavation, requiring a total of 16 mode conversions during the process.
The shield machine that completed its first mode conversion was launched in EPB mode, entered full-face hard rock at ring 46, and at ring 57 simultaneously underwent the transition from split to integral configuration and mode conversion, switching to TBM mode to continue excavation. In this mode, the machine achieves high rotation speed and fast excavation efficiency; compared with the traditional mining method of "soft ground with soft mode, hard ground with hard mode," the dual-mode excavation speed will be 3 to 5 times faster. This mode conversion took 18 days to complete, accumulating rich experience for the preparation work, process coordination, and handling of details for subsequent shield machine mode conversions.
Ziluoshan No. 3 Tunnel on the Xiongan New Area–Xinzhou High-Speed Railway (Shanxi Section) Breaks Through
下一篇Left-Line Shield Tunneling Smoothly Launched for the Yalujiang North Street Station–Wenchu Road Station Section of Shenyang Metro Line 6

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)