1. Reestablish the centerline survey: reestablish the road design centerline, re-survey each point on the road centerline, and proceed to construction surveying after confirming there are no errors.
2. Set out side stakes: measure the road width from the road centerline, and drive wooden (side) stakes at 5 m, 10 m, or 15 m intervals at 0.5—1.0 m outside the side lines on both sides of the road.
3. Measure elevations: measure the road center elevation and mark it on the side stakes (i.e., the “red mark”) for construction use.

2024-10-08 13423 0

2024-09-30 13142 0

2024-09-20 12919 0

2024-09-13 13091 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)