On November 7, good news came from the Tianfu Renshou Avenue, the southern extension of Chengdu's Tianfu Avenue: the Z2 line of the Fengziding Tunnel in the Er'e Mountain section achieved breakthrough, meaning both tunnels along the entire section are now fully connected, laying a solid foundation for the whole line to open to traffic next year.

Breakthrough of the Z2 line of the Fengziding Tunnel
Tianfu Renshou Avenue is a key project in accelerating the overall layout of the 'one pole, one axis, one block' in the Sichuan portion of the Chengdu-Chongqing Economic Zone—specifically the 'one pole,' the Chengdu metropolitan area growth pole—and in building Renshou County's comprehensive three-dimensional transportation network of 'five expressways, five railways, five verticals and five horizontals.' It has a total length of 38.6 kilometers. The Er'e Mountain section under construction is 12.459 kilometers long, with a design speed of 80 km/h; the embankment section has eight lanes in both directions with a total width of 45.5 meters and a 9-meter-wide landscaped median; the tunnel section is designed as four bores with eight lanes in both directions.
It is understood that the eight one-way tunnels, totaling 10.5 kilometers, are the bottleneck works of the entire project schedule. Since construction began, the contractor has combined advanced geological forecasting and monitoring measurement data to establish a full-tunnel intelligent monitoring system, achieving intelligent, visualized and dynamic management of key areas at the tunnel face and high-risk points in critical processes, greatly improving the level of tunnel safety and quality control. As of now, all tunnels in this section have been fully connected.
After Tianfu Renshou Avenue opens to traffic, it will connect with Tianfu Avenue, allowing a direct southward drive from Chengdu to Renshou county seat and bringing convenience to residents of both places. At the same time, the convenient transportation will further improve Renshou County's locational advantages, accelerate its full integration into Chengdu's coordinated urban development, speed up the release of county-level resources such as space, distinctive industries and ecological development, and drive high-quality economic and social development in Renshou County.
Wuhan Institute of Rock and Soil Mechanics Reveals Water Molecule Adsorption Behavior on the External Surfaces of Kaolinite Under Extremely Low Relative Humidity
下一篇Left Tube Excavation at Zhongliangshan Tunnel Entrance of Chongqing-Wuhan Expressway Double-Track Project Exceeds 2,000 Meters

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)