On the eve of the Mid-Autumn Festival, two Zhongrui ZJD7000/1200 reverse circulation drilling rigs successfully met at the Xihoumen Road-Railway Bridge of the Ningbo-Zhoushan Railway in Zhoushan, Zhejiang, celebrating a reunion for the Mid-Autumn Festival!
Rig No. 2, the 7-meter drilling rig, will follow Rig No. 1, the 7-meter drilling rig, to embark on its journey of building the world's largest-diameter bridge engineering piles, pressing the accelerator key for the bored pile construction of the bridge's main piers!

Since the Xihoumen Road-Railway Bridge of the Ningbo-Zhoushan Railway was awarded for construction on October 28 last year, it has progressed smoothly under the leadership of the professional teams of China Railway Major Bridge Engineering Group. The 6.3-meter-diameter engineering piles constructed with the ZJD7000/1200 reverse circulation drilling rig are currently the world's largest bridge engineering piles. The bridge has a main span of 1,488 meters and is the first sea-crossing bridge in China to feature an open caisson foundation; it is the world's first embedded deep-water open caisson foundation. With both 7-meter drilling rigs deployed at the construction site, they safeguard the completion of the civil engineering targets for the entire bridge.
Further Reading and Sharing
The Xihoumen Road-Railway Bridge of the Ningbo-Zhoushan Railway is a key controlling project of the entire Ningbo-Zhoushan Railway line. With its large scale, novel bridge structure, and high technological content, it is a super sea-crossing project that pushes the limits. Once completed, the bridge will become a landmark project among China's high-speed railway sea-crossing bridges. The completion of the Ningbo-Zhoushan Railway will end the history of Zhoushan having no railway access, realize the "one-hour high-speed rail traffic circle" of Zhejiang Province, strengthen the integration effect between Ningbo and Zhoushan, accelerate the integration of Ningbo and Zhoushan into the "Belt and Road" and the Yangtze River Economic Belt, help the Zhejiang Zhoushan Archipelago New Area accelerate the realization of the "one body, one circle, five island groups" development goal, and complete the last "piece of the puzzle" for Zhejiang's goal of "high-speed rail access in every city."
Celebrating National Day and the Anniversary of the Founding of the PRC: The Little Green Corps Invites You to Witness the Beauty of China Through Construction!
下一篇A National Day Tribute! DMP Method Enters Guangdong for the First Time — Impressive!

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project