During cast-in-place pile construction, when concrete is poured underwater, a certain over-pour amount is required to ensure the strength of the pile-head concrete. The over-poured portion at the top of the pile must be chipped away, a process we call pile-head treatment. As the last important procedure in pile foundation engineering, how is pile-head treatment done? Here is an on-site "six-step" demonstration for your reference!

Provisions of the Technical Code for Building Pile Foundations
1. Surveying and setting out
Level surveying is used to mark out the actual pile-top elevation, uniformly identified with red paint.

Construction setting-out

Red paint marking
2. Circumferential cutting with a toothless saw
Use a toothless saw to cut circumferentially around the pile head to a depth of 3-4 cm, then use a pneumatic pick to chip a V-shaped groove from top to bottom along the pile head to peel off the concrete. The main reinforcement must not be damaged during circumferential cutting.

Circumferential cutting

Chipping the V-shaped groove
3. Exposing the pile-head reinforcement
Use a pneumatic pick to peel the main reinforcement from top to bottom along the pile head.

Peeling off concrete with a pneumatic pick

Formed pile-head reinforcement after exposure
4. Cutting off the pile head
After all reinforcement is exposed, drill horizontal breaking holes at 20 cm circumferential spacing at 3 cm above the pile-top elevation using a pneumatic drill. Insert steel chisels into each breaking hole and strike them repeatedly back and forth so that the concrete breaks off along the circumferential breaking holes.

Breaking holes drilled with a pneumatic drill

Repeatedly striking the steel chisel with a sledgehammer
5. Hoisting away the pile head
Drill lifting holes in the already broken pile head, insert steel chisels, and use lifting equipment to hoist out the broken and detached pile head. The lifting equipment should raise and lower vertically and must not sway from side to side, to avoid the pile head tipping over and bending the main reinforcement of the pile foundation into sharp kinks.

Hoisting away the pile head
6. Pile-head cleaning
Pile-head cleaning involves manually chipping away excess concrete and cleaning the top, forming a section that is slightly higher in the center and slightly lower around the edges, ensuring the pile-top surface is flat and dense.

Manual chipping of excess concrete

Finished pile head after cleaning
Total investment of 227.2 billion yuan: 25 major infrastructure projects commenced in January!
下一篇Three Teams Depart at Night! Racing to Join the 'National Team'!

2024-09-29 13335 0

2024-09-20 13336 0

2024-09-20 13180 0

2024-09-19 12457 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)