Guangzhou Huadu Infrastructure Anti-Floating Anchor
194 casing, 200MM hole, 30m deep, sand layer + rock stratum

01. Machine Model





Machine Model
Kongshan KS800 multifunctional anchor drilling rig
Machine Features
Dual-purpose water and air, one machine with multiple functions
Anti-floating anchors, anchor cable anchoring, slope support, single/double-tube high-pressure jet grouting, tunnel grouting, large-diameter down-the-hole rock drilling, foundation pit casing, core drilling, micro piles, steel pipe piles, etc.
02. Construction Site



Construction Site
Huadu District, Guangzhou City, Guangdong Province
03. Construction Process



Construction Process
Process: anti-floating anchor
Stratum: sand layer + granite
Hole diameter: 200MM
Hole depth: 30M
Drill bit: 194MM
Impactor: 55A
Drill pipe diameter: 89MM
Drill pipe length: 2M
Casing diameter: 194MM
Casing length: 2M
04. Construction Results



Construction Angle
Construction angle: 90 degrees
Construction Efficiency
Construction efficiency: 2m/min
Changzhou Yuchai's Gong Zunguo Awarded Wujin District "Gold Medal Worker" Title
下一篇Exhibitor Highlights of the 16th BICES: SKS Hydraulic Technology Co., Ltd.

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)