Stratum Conditions
Location (Province): Jiangsu
Location (City): Wuxi
Drilling Rig Model: SJL-120 jet grouting rig
Drilling Tool Configuration: Ammann 142 series multi-hole drill bit, drill pipe, flow divider
Process Type: Jet grouting water cut-off
Construction Process: MJS method
Stratum Conditions: 1-4 m backfill layer,
4-20 m clay layer
Construction Angle (°): 90
Pile Diameter (mm): 2000
Hole Depth (m): 20

Construction Process
Construction Configuration:
One Ammann SJL-120 drilling rig
Backend Configuration:
One 230 high-pressure pump
One 165 high-pressure pump
One 90E high-pressure pump
One 9 m³ air compressor
Nozzle selected: 2.8

Construction backend configuration diagram

1. Determine the position of each pile as required;
2. Install a 280 mm drill bit on the pilot-hole drilling rig for pilot drilling. During construction, pay attention to the penetration rate to prevent deviation, and remove the drill pipe after reaching the required depth;
3. After installing the drill bit on the SJL-120 drilling rig (clamped by the inner clamp), align it with the hole position as required, adjust the verticality, and set the outriggers firmly;


4. Test and check whether the high-pressure pump, mixing station, air compressor, nozzle, flow meter, pressure sensor, backend data transmission terminal and drilling rig receiving module display, data recording, etc. are normal;
5. Seal the grouting nozzle and cutting water nozzle with transparent tape, connect the drill pipes in sequence (check the sealing rings when connecting the drill pipes), and finally install the flow divider;

Ammann engineer providing on-site guidance
6. Start the air compressor, high-pressure pump and mixing station. The 230 high-pressure pump has a grout pressure of 40 MPa, the 90E has a suction pressure of 15 MPa, the air pressure is 1.0 MPa, the 360° swing jet rotation speed is 6 r/min, and the step stroke is 30 mm/min. During construction, pay attention to changes in rotation pressure and grout return conditions. After removing the drill pipe, clean it promptly to prevent nozzle blockage.
——Ammann Drilling Rig After-sales Service: Wang Bing


Post-construction Reinforcement of a Basement: Construction of Anti-floating Anchors in 150 mm Holes at a Depth of 35 Meters
下一篇Great News! Deadline Extended!

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)