近日,随着“大禹•绿城3号”盾构机刀盘破土而出,郑州地铁8号线01标02工区梧桐街出入场右线盾构顺利实现贯通,提前25天完成了节点目标,这也是该标段首个实现贯通的区间。
梧桐街出入场右线全长907米,覆土厚度6~12.7米,为黏质粉土地层,其中要侧穿一座地下油库,侧穿段全长约为61米,最小水平距离16.4米。“大禹•绿城3号”盾构机自天健湖站始发后,沿科学大道北侧绿化带依次下穿金柏路、规划化工北路,在安全侧穿大桥石化科学大道加油站配房及地下油库后,顺利到达梧桐街出入场线。
掘进过程中,项目部严格控制掘进参数,加强测量监控,保证掘进轨迹符合设计的曲线路径。同时,项目精心组织,各项施工工序有效衔接,创造了单班最高12环的掘进记录,确保盾构施工高效进行。“大禹•绿城3号”盾构机在经过检修后,将继续投入到梧桐街出入场左线紧张的施工当中。
"Jinggangshan" Large Shield Machine Launched for Shenzhen Metro Line 14 Utility Tunnel Project
下一篇First Shield Machine 'Gongjian No.1' Successfully Launched in Section 3 of Phase I of Hefei Rail Transit Line 8

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)