8月7日12时许,伴随着盾构机的轰鸣声,佛山地铁“天佑66号”盾构机破土而出,桂城站~南海广场站区间右线顺利贯通,至此桂城中心区域迎来了佛山地铁三号线首条双线贯通隧道,该线北段又完成了一重要施工节点。
桂城站~南海广场站区间采用土压平衡盾构机掘进,左线于2021年1月12日贯通,右线于2021年4月6日始发,全程沿南海大道敷设,全长781米,地面交通繁忙,沿线有供水、燃气、通信等多种管线,两侧毗邻多栋建筑物,安全风险管控要求高。该区间地质复杂,包含全断面富水砂层、凸起岩脉。
Right-line Tunnel of the Shield-Bored Section from Beijiao Xincheng Station to Gaocun Station on Foshan Metro Line 3 Breaks Through