7月22日下午,随着一声炮响,隧道内传来阵阵欢呼呐喊声。在历经380多个日夜艰苦卓绝的浴血奋战后,渝昆高铁昭通隧道迎来了进口至1号横洞平导的顺利贯通,极大地鼓舞了全体参建人员的士气。标志着昭通隧道进口至1号、2号横洞 3603米平导段全线贯通。
渝昆高铁昭通隧道采取“2横洞+2斜井+平导”的辅助坑道施工方案,平导全长10028米。这次贯通的平导段长2403米,平导穿越可溶岩地层,地质条件复杂多变,施工安全风险极高。
据悉,昭通隧道进口至1号横洞、2号横洞平导段的全线贯通,标志着又一关键线路施工的如期落地,为下一步进入煤系地层施工提供了巷道式通风条件,同时也打通了进口工区运输生命线。