Wawushan in Sichuan Steadily Advances Construction, Completing Output Value of 450 Million Yuan

2021-07-20 1752 0人评论

Since the start of construction on the Wawushan Expressway project, the engineering team, supervision party, and construction contractor have coordinated and cooperated with each other to steadily advance the project while ensuring safety and quality. To date, an output value of 450 million yuan has been completed.

At the No. 1 beam yard and the K1 section construction site, workers were seen fabricating rebar and constructing curing pipes and anti-slide piles. At the same time, engineering team staff, together with project supervisors and safety supervision personnel, were inspecting the craftsmanship quality of beam slab rebar fabrication and the safe construction of anti-slide piles, and reminding the on-site construction managers about construction safety and quality.

At the Wangguan Bridge construction point, workers were tying and welding bent cap rebar and carrying out concrete construction. The No. 5 and No. 6 main piers of the Maliuping Grand Bridge have been capped, and workers are constructing the superstructure bent caps, while construction of other bridge piers is also proceeding methodically as planned.

Deng Qing, on-site manager of the Wawushan Expressway project advancement team, introduced that the lower structure construction of the No. 5 and No. 6 main piers of the Maliuping Grand Bridge has been completed, and superstructure construction is now underway. Two beam yards for the Wawushan Expressway project have been completed, and seven beam slabs have been produced. To date, the Wawushan Expressway project has completed an output value of 450 million yuan.


评论 (0)

TOP