6月15日,随着最后一次爆破作业的完成,漳州漳武高速公路(南靖段)天岭隧道左洞顺利贯通,实现控制性工程阶段性突破,为漳武高速年底主体基本建成奠定基础。
漳州漳武高速全线共4座隧道,天岭隧道为全线最长隧道,全长4889米,是项目关键控制性工程。隧道进口端洞口地势陡峭,且桥隧相连,桥梁台背与隧道洞门之间最小距离为0.5米。参建单位结合现场实际地形,优化隧道进洞施工方案,提前5个月转换为正洞施工。洞内地质复杂,横穿10处断层及破碎带不良地质,施工安全风险高,参建单位攻克了地形限制、富水破碎围岩、近临27米周边引水隧洞等难题,历经17个月实现左洞贯通。
330-Ton Shield Machine Cutterhead Successfully Lowered into Shaft for Zhanjiang Bay Undersea Tunnel
下一篇270 Meters! East Cable Tower of Lingdingyang Bridge on the Shenzhen-Zhongshan Link, the World's Tallest Sea Bridge, Successfully Tops Out

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)