On January 29, the fourth shield TBM "Yuehai No. 25" was successfully launched on Section A6 of the Pearl River Delta Water Resources Allocation Project. To date, Section A6 has completed the launch of all four shield TBMs across the two lines of two working shafts.
Working Shaft GZ13 has two shield tunneling lines. "Yuehai No. 25" is an earth pressure balance shield machine on the right line, with a cutterhead diameter of 6.28 meters. The tunneling direction is from east to west, from Working Shaft GZ13 to Working Shaft GZ12, with a total section length of 2,548.49 meters. It will pass beneath a large number of residential buildings, factories, farmland and other structures and buildings, in areas with dense surface populations, making construction highly difficult.
As Working Shaft GZ13 is the last working shaft in Section A6 to complete main structure construction, in order to successfully achieve the milestone target of launching "Yuehai No. 25," the project department optimized and integrated resources, adjusted personnel allocation, carefully organized and planned, and implemented a shift system to ensure 24-hour construction. Within 28 days, all preparatory work for "Yuehai No. 25" was completed, from shield TBM entry, installation, lowering into the shaft, to commissioning and readiness for launch. Each process was scheduled with tight coordination while remaining orderly, ensuring the shield TBM was launched on schedule.
Previously, another shield TBM on the left line of Working Shaft GZ13, "Yuehai No. 24," was successfully launched on January 6 and has now advanced 26.6 meters. The successful launch and tunneling of the two shield TBMs have strengthened confidence for the project to embark on a new journey in 2021. All builders will continue to uphold the corporate spirit of "utmost precision and sincerity, ever better and newer," ensuring quality, quantity and safety, and forging ahead to advance the construction of the Pearl River Delta Water Resources Project.
New Record: 'Yuehai No. 37' on Section B3 of the Pearl River Delta Water Resources Allocation Project Advances 18 Rings in One Day
下一篇Beijing East 6th Ring Road Reconstruction Project Set to Begin Underground Journey

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)