The CREC Shanhe No. 005 earth pressure balance shield machine (φ6980mm electric drive) successfully completed assembly, commissioning, disassembly and loading at the factory earlier and was shipped to the China Railway No. 5 Bureau project site on Chengdu Rail Transit Line 9, marking that CREC Shanhe's shield machines have stepped out of Changsha and embarked on a new journey.
CREC Shanhe No. 005 earth pressure balance shield machine
The huge machine, shaped like a "flood dragon," encountered unavoidable difficulties during transport. Because the shield body was too large and the journey to Chengdu was long, transporting it by flatbed trailer would exceed width, weight and height limits. Faced with these three excesses, it was decided to disassemble the shield body and ship it to Chengdu by water.
TC arrival photo, waiting for the shield body
Shield body arrives at the site
Due to the limited width of the site, the shield machine was launched in separated sections. Only the main shield machine and the first two trailers could be placed in the shaft; the remaining trailers could only be lowered into the launch shaft after the main machine had tunneled a sufficient distance. At this point, connecting the pipelines between the surface and the shaft became the difficulty of the work. To make it easy to distinguish pipeline types and accurately locate lines in case of faults, the pipelines were classified and arranged on racks. To ensure the quality of cable wiring and prevent interference between lines, the process requirements were particularly precise.
Completed installation of front shield motors
Front shield lowered into the shaft, installing the man lock
Middle shield lowered into the shaft and connected to the front shield, preparing to install the erector
Installing the screw conveyor
CST0005# has successfully completed pre-launch work, and the machine has passed acceptance
After more than two weeks of assembly, pipeline connection and commissioning, CST0005# has successfully completed the pre-launch work and passed machine acceptance. It is currently assembling the negative rings, and a new journey has already begun.