Industrial Water Supply Plant at Haiziwan Reservoir in Shawan County, Tacheng Officially Breaks Ground with Estimated Investment of 25 Million Yuan

2016-03-09 658 0人评论
Large excavators methodically dug the main pipe trench for the water supply pipeline while construction workers busily pressed ahead with the work... Recently, the industrial water supply plant at Haiziwan Reservoir in Shawan County, Tacheng City, officially began construction. This is also the first water conservancy project to start construction in Tacheng Prefecture this year.
Nie Weiguo, director of the Shawan County Water Conservancy Bureau, said: "The start of construction of the Haiziwan Reservoir industrial water plant marks the full-scale commencement of water conservancy financing projects in Shawan County this year. The water conservancy department will strive to ensure the water plant is completed on schedule in the shortest possible time, without delaying farmers' spring plowing and production, and laying a solid foundation for water use in the Liumaowan Industrial Park."
The water plant's water source is Haiziwan Reservoir, with an annual reservoir capacity of 18.25 million cubic meters. Once the plant and its connecting water supply pipeline are completed, they will supply 8 million cubic meters of water per year to the Liumaowan Textile Industrial Park.
The water plant project has an estimated investment of 25 million yuan. The water supply pipeline currently under construction passes through land in some villages of Laoshawan Town, Liumaowan Town and Shanghudi Township, and efforts are being made to complete construction by March 15 so as not to affect farmers' spring sowing. The water plant is scheduled to start construction on March 15 and be completed before May 30.
Wang Fangjun, project manager of the Shawan Project Department of China Railway First Group Municipal and Environmental Protection Engineering Co., Ltd., said: "We will complete the water plant project to high standards, with strict requirements and high quality, strictly follow the established schedule, and complete all planned works with guaranteed quality and quantity, making our contribution to the people of Shawan."