据市公用事业管理局桥梁管理处工作人员介绍,新水东大桥水下部分共有两个主桥墩,分别为3#墩和4#墩,每个墩分别有8根钻孔灌注桩。其中,3#主桥墩位处河床,地质复杂、岩层坚硬、相邻桩基间的地质岩层差异较大,给施工带来较大困难。自2012年12月26日开始施工以来,项目部人员通过增加钻机设备和人员投入、实行24小时人员轮班不间断施工等措施,合理安排,连续奋战,终于在13日晚上9点完成了3#主桥墩的最后一根桩基的混凝土灌注施工。至此,新水东大桥水下部分主桥墩桩基施工已赶在汛期来临前全部完成,为接下来的承台和墩柱的施工浇筑奠定了坚实的基础。