As of June 8, 2026, a total of1,548 pileshave been completed in the overwater pile driving operations for Phase III of the Tonghai Port Area project, and overall pile driving work is90%complete.

This means that although a large number of critical foundation piles have been installed and the wharf foundation has essentially taken shape, the project has not yet reached a fully "completed" status of 100%, with some remaining finishing work still underway.
Previously, on March 23, 2026, when all underwater pile driving for the project's No. 3 berth was completed, the overall pile driving completion rate was 60%.
评论 (0)