In 2024, Alxa League plans to implement 134 major construction projects with an annual investment of 44.57 billion yuan. As of the end of March, 109 projects had started or resumed construction, a start/resumption rate of 81%; completed investment was 8.15 billion yuan, 18.3% of the annual plan, an increase of 40 million yuan over the same period last year. Among them, 50 of 50 continued projects resumed construction, a resumption rate of 100%, with completed investment of 5.33 billion yuan, 32.2% of the annual plan; 59 of 84 new projects started, a start rate of 70%, with completed investment of 2.81 billion yuan, 10% of the annual plan.
— By sector:
Agriculture, animal husbandry, forestry, grassland and water projects: 12, with an annual planned investment of 3.05 billion yuan; 11 started, a start rate of 91.7%; completed investment of 460 million yuan, 15.1% of the annual plan;
Energy projects: 17, with an annual planned investment of 19.13 billion yuan; 15 started, a start rate of 88.2%; completed investment of 3.1 billion yuan, 16.2% of the annual plan;
Major industrial development projects: 60, with an annual planned investment of 16.62 billion yuan; 52 started, a start rate of 86.7%; completed investment of 4.09 billion yuan, 24.6% of the annual plan;
Transport infrastructure projects: 16, with an annual planned investment of 4.35 billion yuan; 8 started, a start rate of 50%; completed investment of 310 million yuan, 7.1% of the annual plan;
Urban (including park) infrastructure projects: 23, with an annual planned investment of 1.22 billion yuan; 18 started, a start rate of 78.3%; completed investment of 160 million yuan, 13% of the annual plan;
Social undertakings projects: 6, with an annual planned investment of 210 million yuan; 5 started, a start rate of 83.3%; completed investment of 30 million yuan, 13.5% of the annual plan.
— By jurisdiction:
League-level departments, individually and bundled: 19, with an annual planned investment of 6.41 billion yuan; 10 started, a start rate of 52.6%; completed investment of 590 million yuan, 9.3% of the annual plan;
Alxa Left Banner: 19, with an annual planned investment of 9.58 billion yuan; 18 started, a start rate of 94.7%; completed investment of 1.72 billion yuan, 18% of the annual plan;
Alxa Right Banner: 13, with an annual planned investment of 5.4 billion yuan; 13 started, a start rate of 100%; completed investment of 1.45 billion yuan, 26.7% of the annual plan;
Ejin Banner: 18, with an annual planned investment of 2.36 billion yuan; 15 started, a start rate of 83.3%; completed investment of 310 million yuan, 13% of the annual plan;
Alxa High-tech Zone: 40, with an annual planned investment of 15.17 billion yuan; 35 started, a start rate of 87.5%; completed investment of 3.08 billion yuan, 20.3% of the annual plan;
Luanjingtan Ecological Migration Demonstration Zone: 15, with an annual planned investment of 4.57 billion yuan; 12 started, a start rate of 80%; completed investment of 860 million yuan, 18.9% of the annual plan;
Ceke Port Development Zone: 10, with an annual planned investment of 1.1 billion yuan; 6 started, a start rate of 60%; completed investment of 140 million yuan, 12.9% of the annual plan.