82m (Φ2.8m) Ultra-Deep Pile Completed in Two Days: Jintaiguo Four's Rotary Drilling Rigs Make Their Debut in Yunnan

2023-12-01 1593 0人评论

Recently, the SH58F multi-functional rotary drilling rig, a new product from Jintai Guosi, made its debut in the pile foundation construction of the Liming Bridge in the Yuwei Expressway section in Lijiang City, Yunnan Province. The project features large bore diameters, great depths, hard strata, abundant sand layers, and easy hole collapse, with complex techniques and a tight schedule, making construction somewhat difficult. The Jintai Guosi SH58F has now completed the sixth ultra-deep bored cast-in-place pile with a depth of 82 m. With fast construction speed and high hole-forming quality, it has won high recognition from the contractor.

SH58F Multi-functional Rotary Drilling Rig

The Yuwei Expressway section-Liming Bridge project is an important component of the Yunnan-Tibet major transportation corridor and a major component of Yunnan Province's Greater Western Yunnan Tourism Loop and the Greater Shangri-La Tourism Loop. It is of great significance for maintaining stability in Tibetan areas, promoting ethnic unity in border regions, and driving local economic development.

Rendering of Liming Bridge

Stratum Distribution Description

Strata of the project: 0 m–27 m is a pebble layer, 27 m–30 m is strongly weathered mudstone, 30 m–49 m is shaly mudstone, 49 m–70 m is a sand layer, 70 m–75 m is strongly weathered sandy mudstone, and 75 m–82 m is a sand layer. The actual construction strata are relatively hard and have a sand content of more than 30%, making hole collapse likely. In response to these geological characteristics, the site adopted the process method of "rotary drilling + reverse-circulation desander" for construction. Based on summarizing the experience from the first ultra-deep pile, the contractor and Jintai technical personnel adhered to the principle of "adapting measures to the pile and taking multiple measures simultaneously" to ensure hole-forming quality. The current pile-forming efficiency has gradually increased from 60 hours per pile to 48 hours per pile, with overall machine efficiency improved by more than 20%, providing a strong guarantee for the subsequent construction schedule.

The SH58F is a new large rotary drilling rig with China IV emissions developed by Shanghai Jintai to adapt to working conditions such as large diameters and ultra-deep piles in rock strata. It has eight major advantages that are unstoppable!

1. A new-generation China IV Cummins engine, powerful with low fuel consumption.

2. Strong torque and lifting capacity make it the ** equipment for large-diameter ultra-deep piles in complex strata.

3. Solid guide rail technology, precision machined and formed, delivering high hole-forming quality and low noise.

4. Professional-grade hydraulic components with high output power.

5. Multi-gear control, rock-entry adaptive technology, and visualized operation for efficient drilling.

6. Single-layer long-drum dual heavy-duty reducer main winch; the single-layer drum can achieve an effective drilling depth of up to 136 meters.

7. Reasonable chassis layout with large space and convenient maintenance.

8. Visualized technology for the pressure table, reducing drill pipe failures and improving construction efficiency.