Total Investment of 7.9 Billion Yuan! Construction Bid Awarded for Dong'e-Yanggu Expressway

2023-08-28 2665 0人评论

Civil Engineering Construction of the Dong'e–Yangu Highway PPP Project

I. Project Overview

This project is located in the Yellow River alluvial plain of northern Shandong, with flat terrain and a dense network of ditches, canals, and rural roads. The route length is 58.552 km, with 12.44 million m³ of fill and 430,000 m³ of excavation. Structures (excluding interchange areas) include: 1 extra-large bridge of 1,715.5 m, 3 large bridges of 350 m, 8 medium bridges of 543 m, 2 small bridges of 75 m, 24 separated interchanges, 97 passages (52 passage bridges and 45 culvert-type passages), and 41 culverts; 2 hub interchanges, 4 general interchanges, and 4 ramp toll stations; 1 service area, 1 maintenance work area, and 1 monitoring and communications sub-center each; and 2 interchange connecting lines.

Project investment:Total estimated investment7,911,087,900 yuan.

Section division:Divided into 3 civil engineering sections. The specific division is as follows:

Section DYTJ-1:Civil engineering works within K0+000–K16+000, with a main line length of 16 km and the Yushan Interchange connecting line of 5.198 km (including pavement works); pavement works within K0+000–K29+000, with a main line length of 29 km.

Section DYTJ-2:Civil engineering works within K16+000–K29+000, with a section length of 13 km.

Section DYTJ-3:Civil engineering and pavement works within K29+000–K58+551.921, with a main line length of 29.552 km and the Yangu North connecting line of 4.118 km (including pavement works).

Planned construction period:The tentative construction period for Sections DYTJ-1 and DYTJ-3 is 763 calendar days, and for Section DYTJ-2 is 671 days, calculated from the commencement date specified in the commencement notice issued by the supervisor.

II. Bid Award Information

Section DYTJ-1

First place: China Railway 23rd Bureau Group Co., Ltd.

Second place: China Railway 16th Bureau Group Co., Ltd.

Third place: China Railway 14th Bureau Group Co., Ltd.
Section DYTJ-2

First place: China Railway 22nd Bureau Group Co., Ltd.

Second place: China Railway 23rd Bureau Group Co., Ltd.

Third place: China Railway 21st Bureau Group Co., Ltd.
Section DYTJ-3

First place: China Railway 16th Bureau Group Co., Ltd.

Second place: China Railway 22nd Bureau Group Co., Ltd.

Third place: China Railway 20th Bureau Group Co., Ltd.